20
people are needed to volunteer each Sunday from each conference (40 each day).
GCC HAS THREE OPPORTUNITIES
~
1. Sponsoring church (A church commits to
take one Sunday by filling all 20 slots and chooses a volunteer to be Day Captain.)
Note: Churches can invite members from other churches to join them in order to get
the full 20. However, all communication with the Coordinator flows from only one
church.
2. Partnering church (Signs up in blocks
of 5, 10, or 15 volunteers and commits to filling that number from their church
for one or more Sundays, and chooses a volunteer to be Day Captain)
3. Individuals
(Sign up on any, or
all Sundays! Limited to two slots on Sundays that a church has sponsored)
WHEN? September
21, 28; October 5, 12, 19, 26; and November 2: Each Sunday goes from 8 a.m.
to 4 p.m.
WHERE? Begin
first Sunday at Habitat for Humanity, 500 Woodward Avenue, Atlanta, GA. (All other
days, volunteers go directly to the site)
WHY? Serve
others. Build a new home for someone deserving. Be a missionary close to home.
Contact to Sign UP?
Damien
Smith at 770.306.1967 or via email at
Damiensmith2585@aol.com or Joy Ihesinachi at 678.613.5705 or vial email at
jordinia@yahoo.com .
FYI ~ Every volunteer will need to complete a release/waiver form and submit
it to the Habitat leader on the first day of work.
BUILD DATES AND TYPE OF WORK
Day 1
– September 21
Clear crawl space
and paint foundation. Set floor joists. Lay floor decking. Sheath panels and run
exterior walls. Run interior walls. Tie walls together. Straighten and brace. Install
lower porch package.
Day
2 – September 28
Prep and run trusses. Install windows and trim packages.
Install interior framing – wind bracing, deadwood, attic stairs. Deck roof. Install
sub-fascia. Barge rafters and drip edge. Felt roof. Set up for siding – trim, corner
boards, skirt board, drip cap and starter strip.
Day
3 – October 5
Shingle roof. Insulate walls and ceiling. Begin
siding and caulking. Install underlayment in kitchen, dining room and bathroom.
Day 4
– October 12
Finish insulation.
Finish siding and caulking. Begin painting exterior – siding, foundation, window
trim. Build side porch and ramp.
Day 5
– October 19
Finish exterior
painting. Begin interior painting. Install baseboard, window sills and miscellaneous
interior trim. Install kitchen cabinets and countertops. Begin soffit and fascia.
Day
6 – October 26
Touch up exterior painting. Finish soffit and fascia.
Finish interior painting. Install porch railings.
Day 7
– November 2
Install doorknobs
and bathroom hardware. Clean house interior. Touch up interior painting. Complete
miscellaneous items. Rake and clear lot. Landscape. DEDICATE NEW HOME!